Platinum Park Estate – Phase 2



September 2020


Allocation of the next 195 stands to our Top Structure Developers has been successfully completed & sales of building packages are underway

Installation of the internal services to begin in September 2020 & completion is expected May 2021

November 2020


Installation of internal and civil services are well underway together with upgrading work of external road infrastructure

Klerksoord Extension 49
Klerksoord Extension 29
Klerksoord Extension 29
Klerksoord Extension 29
Klerksoord Extension 29
Klerksoord Extension 29
Klerksoord Extension 29




March 2021


Installation of the internal Civil Services are progressing well

Klerksoord Extension 29


April 2021


Installation of the internal Civil & Electrical Services nearing completion

Klerksoord Extension 29


June 2021


Installation of the internal Civil & Electrical Services are completed with the township being Proclaimed July 2021

Klerksoord Extension 29


September 2021


Our Top Structure Developers commence with house construction

Klerksoord Extension 29


October 2021


House construction progressing well

Klerksoord Extension 29


November 2021


50% of the houses either under construction or completed

Klerksoord Extension 29


March 2022


Construction of all houses completed in Phase 2

Klerksoord Extension 29