Platinum Park Estate – Phase 1
We have secured the Platinum Park Estate project, which consists of four extensions yielding a total of 700 residential stands
The property is located 3kms east of the Rosslyn Hub along the R566 and is easily accessible from the N4 and R80 freeways
Construction on the first phase, Extension 28 (consisting of 184 stands) started in January 2019 with the installation of civil and electrical services
JANUARY 2019
Commencement of the installation of the Internal & External Civil Stormwater and Sewer reticulation
FEBRUARY - JUNE 2019
Progressing well with the installation of the Internal Water, Sewer & Stormwater reticulation. Box cutting of internal Road infrastructure commences
JULY 2019
Closing up of the internal Stormwater, Water, Sewer & Electrical conduiting reticulation. Preparation of Internal Road-bed infrastructure commences
AUGUST 2019
Preparation of the Road infrastructure for the tarring process
OCTOBER 2019
Internal Civil reticulation & Road infrastructure of 184 Residential stands completed together with the upgrading of the external Stormwater, Sewer, Water & Road infrastructure
FEBRUARY 2020
Construction of the first 20 houses by our Top Structure Developers commences with the preparation of raft foundations, floor slabs and then super structure and roofs
June 2020
Construction of houses could continue again after lockdown restrictions were eased resulting in the first houses being completed
August 2020
Construction of the 2m high Perimeter Security Wall commenced with in excess of 70 houses either under construction or completed
September 2020
Phase 1 of Platinum Park Estate is SOLD OUT!
September 2021
Construction of all 184 houses completed in Phase 1